The Office of Rail and Road released the estimate of station usage figures for 2018-19 in January 2020 enabling a review of passenger numbers at the recent additions to the
Continue readingCategory: Apperley Bridge [opened]
New stations establish themselves in latest estimates of station usage
New railway stations have established themselves in the latest estimates of station usage for 2016/17 published by the ORR on Friday. A summary of the railway stations discussed in this
Continue readingBradford rail usage booms with new stations
Rail has proven to be a successful contributor towards the uptake of low carbon travel options with Apperley Bridge car park filling up and Low Moor expected to open in
Continue readingApperley Bridge is busier than forecast
Apperley Bridge railway station, which opened on 13th December 2015 has proven to be busier than the forecast expected. This update will be presented to the Bradford sub committee of the
Continue readingApperley Bridge officially opened
Apperley Bridge was officially opened on 18th December. Rail Engineer were on site as the official opening took place.
Continue readingApperley Bridge set to open in December
Apperley Bridge railway station is set to open on 13th December subject to final ORR approval. Source: BBC News
Continue readingApperley Bridge postponed
The opening date for Apperley Bridge has been slipped to Autumn 2015. Click here for the story
Continue readingApperley Bridge Railway Station update – September
Construction continues at Apperley Bridge, with the railway station rapidly approaching completion. Two photos show the progress of the platforms taken on Saturday 19th September. The Leeds bound platform
Continue readingApperley Bridge Railway Station update – August
Apperley Bridge is set to open within the next two months. The station is progressing well with substantial and recognisable parts of the station in place. The photos were taken
Continue readingApperley Bridge Railway Station Update – April 2015
The Bradford District Consultation Sub-Committee is due to meet on 17th April 2015. The following update has been produced for Apperley Bridge Rail Station. WYCA is working with Network Rail and Northern
Continue readingApperley Bridge will open on time
Apperley Bridge is on course to open in August. Click here for the story
Continue readingApperley Bridge Railway Station Update – January 2015
The Bradford District Consultation Sub-Committee is due to meet on 23rd January 2015. The following update has been produced for Apperley Bridge Rail Station. 2.9. Work is progressing well on site
Continue readingTransport Secretary visits Apperley Bridge site
The transport secretary Patrick Mcloughlin has visited the site of the Apperley Bridge Railway Station that is currently being constructed. Click here for the story
Continue readingApperley Bridge and Kirkstall Forge Funding agreed
The Department for Transport has signed off £9.5 million of government funding to deliver two railway stations at Apperley Bridge and Kirkstall Forge on the railway line between Leeds and
Continue reading