First passenger services use Ordsall Chord

The first passenger carrying trains have used the Ordsall Chord this morning. Click here for the article The Independent has reviewed the Ordsall Chord and the impact it will have

Continue reading

Northern set to operate first Ordsall Chord service

The timetable change will see Northern operate the first train with the passengers on Sunday 10 December. The first train is expected to be the 0840 Manchester Victoria to Manchester

Continue reading

Ordsall Chord ready

With a month to go until revenue earning services start using the Ordsall Chord, the Manchester Evening News have visited the construction site to observe the final stages of work

Continue reading

Ordsall chord swoosh completed

The final section of the swoosh bridge for the Ordsall chord was craned into place at the weekend. Click here for the article 

Continue reading

Ordsall Chord work enters final stages

The work on the Ordsall Chord is moving into the final phases of work as workers on site prepare for completion in December 2017. The final phase of the project

Continue reading

Bridge craned in for Ordsall chord

The two arches that form the railway bridge on the Ordsall chord were craned into place on Tuesday. Source: Network Rail

Continue reading

Ordsall Chord works progress over Christmas period

Work on the Ordsall chord and nearby railway lines over Christmas helped ready the local rail network for the changes that are required to support train services over the Ordsall

Continue reading

Ordsall Chord legal challenge dismissed

The court of appeal  has dismissed the legal challenge raised against the process by which permission was granted for the construction of the Ordsall chord. Source: Network Rail

Continue reading

Groundbreaking bridge set for Ordsall chord

The bridge over the River Irwell on the Ordsall chord will be the world’s first ‘squashed tennis racket style’ railway bridge. It will be built as the UK’s first ‘network arch’

Continue reading

Ordsall chord work begins

Work has begun on the Ordsall chord, with engineering works being held to support preparatory works. The chord is expected to open in December 2017. Click here for the article

Continue reading

Judicial review dismisses Ordsall Chord challenge

A judicial review has dismissed a challenge to the route chosen for the Ordsall Chord Source: Network Rail

Continue reading

Lawyer argues Ordsall Chord may never happen

A lawyer has warned that the Ordsall chord may never happen. The claim came following the deferral of a legal challenge to the route chosen for the chord. Click here

Continue reading

Lawyers argue Ordsall Chord decision is flawed

Lawyers representing Mark Whitby have argued that the decision process for the preferred option for the ordsall chord was flawed. Click here for the article

Continue reading

Legal challenge to Ordsall chord

A legal challenge is set to be heard following criticism of the preferred route chosen for the Ordsall chord. Click here for the article

Continue reading

Ordsall Chord given go ahead

The Secretary of State for Transport has given the go ahead for the Ordsall Chord. The Ordsall Chord will cost £85m and will provide a direct connection between Manchester Victoria