Network Rail have confirmed the dates when the railway line through Soham will be closed to enable the construction of the new railway station. Engineers will need to work on or near the track to build the new platform and footbridge. Additional work also needs to take place including ground levelling and track alignment adjustment to make sure the gap between the platform and train meets the required industry standard.
The dates when the railway line will be closed and trains replaced by rail replacement bus services are:
Sunday 14 March
Sunday 21 March
Sunday 2 May
Saturday 22 and Sunday 23 May
Sunday 30 May
Saturday 12 and Sunday 13 June
Sunday 20 June
Sunday 29 and Monday 30 August
Source – Network Rail