Following successful completion of preparatory work, primarily diverting an existing water main, the team on site have now started work to create the embankments for the new station platforms.
Work from now until the end of June will see the creation of embankments for, and the start of construction work on the new platforms, drainage built on the new access road and pilling to support the installation of new signalling and overhead line equipment.
Source: Network Rail